标题: A letter from Johnson & Johnson [打印本页] 作者: 云烁IT服务 时间: 2016-5-20 13:50 标题: A letter from Johnson & Johnson Hi Johnny,
Client confirmed, Jerry is the point of contact on site:
To confirm the tasks:
14th April
Conduct a passive walkthrough wireless survey of the 3 Demo Floors: 19, 20 and 22. The APs have already been installed and the survey is to confirm the current coverage is complete.
15th Apr
Produce the report of the survey conducted on the 14th Apr
18th, 19th and 20th Apr
Conduct a passive mounted wireless survey of 8 Floors: 2,4, 14-18, 21. The APs have not yet been installed and the survey is to determine how many APs are required and where they should be placed.
21st, 22nd and 25th Apr
Produce the report of the passive mounted survey of the 8 floors.
The floors that require a survey on 18th-20th Apr is new information and was not in the resource request, Please add that to this request if possible and confirm